MD, K-RIDE conducted a morning inspection today on the BSRP Corridor-2 (at-grade section), covering the stretch from Mukthinagar (LC-140) to Banaswadi over a corridor allignment length of 2.300 Km (from Ch 6.300 to Ch 4.000).
The site visit reviewed ongoing and proposed at-grade works including earthwork in embankment, ERS, minor bridges and RUBs, along with raising of formation for both BSRP C2 tracks and Indian Railways tracks (two tracks each). The inspection focused on reviewing the alignment feasibility, station locations and construction methodologies.
#BSRP
Key areas of emphasis included handing over of balance private land acquisition and C&R, eviction of IR encroachments, shifting of IR assets such as rails and sleepers, relocation of BWSSB sewer and water lines, removal and shifting of BESCOM electrical utilities, and shifting of IR S&T cables, with the objective of resolving constraints and accelerating project execution.