#BSRP Station Works: Progress Update Yeshwantpur station of Corridor–2 is a 7-floor interchange hub. D-wall works are under progress. 68 out of 106 panels done. KRIDE & CEMINDIA ensure “Safety, Quality & Progress."
#kride #BSRP