✨ Our Pride, Our Capital ✨
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
⭐️ E6 Road ⭐️
• Velagapudi To Anantavaram - 9.844 Kms
• This Road Crossing 9 Junctions
• Maximum Road works Completed Between N9 To N15 Junction
• N15 To N17 Junction Between Works Curbs & WMM Laying Works Going on
• This Road Connect To CBN Sir House Near E6 & N10 Junction
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
😱 60 % Completed - N18 Road 🛣️ ✅
• N Series Last Road
• Connecting E7,E8,E9 Roads Crossing 3 Junctions
• 50 Meters ROW With Walking & Cycling Tracks Avenue plantations
• Road 2+2+2 Each Road 7 meters wirth
• Connectivity To Anantavaram & Nekkallu Villages
• Wmm Top Laying & Curb Works Going on
• First Huge Percentage Completed Trunk Road In Amaravati
• Nearly 60+ % Road Works Completed
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🙏 Budda Statue Renovation Completed ✅
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
⭐️ Star Hotels Rasing In Amaravati ⭐️
1. Daspalla 4 Star Hotel
2. Manjeera Holiday Inn 4 Star Hotel
3. Varun Group Novotel 5 Star Hotel
4. Malaxmi Group Double Tree by Hilton 5 Star Hotel
• Works Going on rapid speed
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🚧 Guntur IRR Works In Progress 🚧
• IRR Phase 3 - 4.25 kms
2+2 lines
• Each road 7.5 meters Wirth
24 meters ROW
•Present Works Side wall drain works Retaining wall works
Box Calverts works Going on
•8 box Calverts
112 to 120 Sewerage UGD man holes
•Project cost 48 cr APCRDA Funding
#Apcrda
#Guntur
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🔥 Krishna River Retaining wall Update 🔥
👉 300 + pilings completed out of 2000
•Wall hight 9 meters
40 /45 Depth Of piling
•Per day Completing 10 To 15 piles
•Target To Complete 2 years From Work Started
•Wall bottom Wirth 1.8 meters Top Wirth 0.6 meters
.Total wall 1.7 kms
• Varadhi To Railway Bridge
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🔥 Bahubali - Iconic Towers - “A” 🔥
• Works Going On Rapid speed
• 4 Hod & 1 GAD Tower Constructing In Super Block E
• Worlds Tallest Secretariat Towers Constricting In Amaravati Hight 230 meters
• HOD 4 Towers B+G+39 Floors GAD Tower B+G+49 Floors
• 32 Acers Land 68.88 Lack SFT Build up Area
• Present Works Diagrid Coloms Core wall Concrete works & Aminity Block Concreting works
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
😍 2 Steel Bridges Status In Amaravati 🏗️
• 128 meters Steel Bridge In Buckingham canal
• 293 Meters Steel Bridge In Kondaveeti vaagu
• Better Connectivity To Prakasam barrage To Seed Access Road
• RHS Bridge Reinforcements Completed Concreting soon
• Seed Access road phase 3 starting Bridge maximum Civil work completed
• Girder launching works in progress
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
✅ Re Pouring Concreting Works in Progress At High Court ⚖️
• High Court B+G+7 Floors 55 Meters Hight 42 Acers Land
• Total 52 Court Halls In 2,4,6 Floors
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱