🔥 N12 Road Huge Changes 🔥
• Important Road In Core Capital Area
• Rayapudi To Sakhamuru 8.6 kms
• Arterial road 50 meters ROW
• Present works MV power Ducts, Storm water Drain Works in Progress
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🔥 Bheema Fabrication yard For GAD Tower 🏗️
👉 Diagrid Coloms, Nord, Beams Fabrication Unit 👈
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🏡 AIS Bungalows - Internal works and Painting works in Progress 🏡
• AIS Bungalows Constricting AGC Super Block D
• Total 100 Bungalows Constricting here
• 75 Secretary Bungalows 25 Principal Secretary Bungalows
• Present Work Internal works & Painting works in progress
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
💧190 MLD Water Treatment Plant Water supply for Amaravati Capital City 💧
• constructing in latest technology
• Plate settlor technology with zero liquid discharge
• Constructing 64 MLD Clear Water Reservoir
• Work going on Rapid speed
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🚨 Gravity Canal Maximum work completed ✅
• 7.83 Kms 815 Acers
• Canal Bed Wirth 40 meters Top Wirth 70 meters Each side 20 meters Green buffer zones
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🔥 N16 road Tar Works 🔥
• Dondapadu To Nekkallu 8.7 kms
• 50 meters ROW Sub Arterial road
• 2+2+2 Lines Each Road 7.5 meters Wirth
• Crossing 7 Junctions
• Present Road Works At CH : 8+200 To 8+700 RHS DBM first Layer Works in Progress
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
🔥 1st Lps Zone Tar Works Starts In Amaravati Zone 7 ( Block - 5 ) 🔥
• Total 7 Blocks 1688 Acers Land
• Key Zone in Capital Region
• In This Zone Covered APCRDA Building, Finance City, Quantum Valley, Bits Amaravati & 4&5 star hotels
• Present Road Works At Block 5 - 25 meters Collector Road DBM first Layer Works going on
• Road 2+2 Lines 7+7 Meters Wirth Road
• Each Carriage Way Having Walking & Cycling tracks
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani. #📽ట్రెండింగ్ వీడియోస్📱
⭐️⭐️ Manjeera 4 Star Hotel ⭐️⭐️
• Hotel Constructing In E3 & N11 Junction
• Allocated 2 Acers Land In Kondamarajupalem Village
• Building Construction 2 Basements G+21 Floors
• Build up area 34602 Sq.m With 255 Rooms
• Present Diaphragm wall works going on
• premium amenities, banquet Hall, health club, gym, spa, swimming pool, speciality restaurant, all day dining
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱
#📽ట్రెండింగ్ వీడియోస్📱
🚨 E5 Road 🚨
• Key Road In Capital Region
• Tadepalli To Ananthavaram 19.4 Kms 60 meters ROW
• Two Sides Service Roads & Elevated Corridor Road
• This Road Crossing Government City & Justice City Middle
• 2 Diamond Circles Only Tunnel Road In Capital Region
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani
😱 16.7 Kms Canal - Palavagu 😳
• Penumaka Reservoir To Dondapadu 16.7 kms
• Penumaka To Secretariat 9.3 kms Bottom Width Of Canal 25 meters
• Top Width Of Canal 65 Meters Green Width of each side 20 meters Total 105 meters
• Secretariat To Dondapadu 7.4 kms Bottom Width 12 Meters Top Width 45 meters Green Width 30 meters each side Total 105 meters
#Apcrda
#Amaravati
#AndhraPradesh
#ShaikNayeemPasha
#AmaravatiCapitalUpdates
@prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱