The Bengaluru Suburban Rail Project is a transformative mobility initiative for the city and it is encouraging to see strong citizen interest in its progress.
It is important to note that KRIDE has made significant strides on several key fronts w.r.t BSRP:-
Alignment approvals for all four corridors of the project, which was a crucial milestone for the execution phase of the project, have been successfully obtained.
Stations work of BSRP, which are Long Lead Items, are progressing well. Station works of Corridors 2 and 4 are advancing very well and major construction activities are underway.
In addition, land acquisition for Corridor 2 has been completed 100%, while land acquisition for Corridor 4 is in progress. Land acquisition process has also been initiated for Corridor 1 and corridor 3 after the approval of alignment. Bengaluru’s long-term mobility needs these Corridors and we are moving in this direction accordingly.
KRIDE remains firmly committed to delivering citizen-centric urban mobility infrastructure for Bengaluru. The organisation values and appreciates constructive engagement from citizens and stakeholders, which plays an important role in strengthening and accelerating the city’s infrastructure development.
#kride
![kride - Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction - ShareChat kride - Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction - ShareChat](https://cdn4.sharechat.com/bd5223f_s1w/compressed_gm_40_img_490071_3456f980_1773396488851_sc.jpg?tenant=sc&referrer=pwa-sharechat-service&f=851_sc.jpg)