The Bengaluru Suburban Rail Project is a transformative mobility initiative for the city and it is encouraging to see strong citizen interest in its progress.
It is important to note that KRIDE has made significant strides on several key fronts w.r.t BSRP:-
Alignment approvals for all four corridors of the project, which was a crucial milestone for the execution phase of the project, have been successfully obtained.
Stations work of BSRP, which are Long Lead Items, are progressing well. Station works of Corridors 2 and 4 are advancing very well and major construction activities are underway.
In addition, land acquisition for Corridor 2 has been completed 100%, while land acquisition for Corridor 4 is in progress. Land acquisition process has also been initiated for Corridor 1 and corridor 3 after the approval of alignment. Bengaluru’s long-term mobility needs these Corridors and we are moving in this direction accordingly.
KRIDE remains firmly committed to delivering citizen-centric urban mobility infrastructure for Bengaluru. The organisation values and appreciates constructive engagement from citizens and stakeholders, which plays an important role in strengthening and accelerating the city’s infrastructure development.
#kride
The 55th #NationalSafetyWeek was observed across all BSRP–KRIDE project stations under the theme “Engage, Educate & Empower People to Enhance Safety.”
Through awareness drives, health camps, mock drills and safety activities, teams reaffirmed that Safety is Everyone’s Responsibility.
Interactive activities including PPE races, safety quizzes, drawing competitions, mock drills, toolbox talks, First-Aid & CPR training, safety marathons and walkathons kept safety learning engaging.
The initiatives witnessed enthusiastic participation from teams across stations including Hebbal, Yeshwanthpur, Myadarahalli, Shettihalli, Jakkur, Carmelaram, Huskur and Bellandur, strengthening the safety culture across the BSRP project.
#SafetyFirst #kride
#Surging_Ahead
#Progress_on_track_at_Myadarahalli
Station construction works at Myadarahalli station of Corridor 2 of BSRP is progressing well.
Can you suggest a caption for this work progress photo captured today?
Comment below
#CaptionThis #WorkInProgress #KRIDE #kride
How informed are you about Bengaluru Suburban Transport Project (BSTP)?
Answer the following question in comment below #kride
#Morning_Inspections
Shri Lakshman Singh, MD, K-RIDE, along with senior officers and contractors, inspected the station works at Hennur and Horamavu under Priority-1 section of Corridor 4 of BSRP.
He appreciated the completion of 100% S&T utility shifting and directed the station Contractor to expedite station works within the stipulated timeline. #kride
#Breaking_Now
Catch a glimpse of the rapidly progressing BSRP
Corridor 4, Bellandur Road Station Works here.
It's part of the Package C4A, awarded to RVNL-RPPL JV.
#bsrpstationworks
#Galloping_Milestones
Know more on the progress update of Shettyhalli Station works under Corridor 2 (Mallige Line) as the Manager concerned shares key updates on the ongoing construction activities.
#ShettyhalliStation #Corridor2 #MalligeLine #RailInfrastructure #kride
How informed are you about Bengaluru Suburban Transport Project (BSTP)?
#kride
Answer the following question in comment below
Managing Director, K-RIDE, Er. Lakshman Singh, IRSE, delivered a presentation on “Building Tomorrow’s Cities with Integrated Rail Network” at Concrete Panorama & Deminar 2026, organized by the Indian Concrete Institute, Bengaluru Centre. #kride
His address highlighted the critical role of integrated rail systems in enabling sustainable urban growth and future-ready infrastructure. K-RIDE remains committed to shaping resilient, connected cities through transformative rail solutions.
Managing Director Er. Lakshman Singh, IRSE, graced the Inaugural Program of Concrete Panorama & Deminar 2026, organized by the Indian Concrete Institute, Bengaluru Centre, as the Guest of Honour.
This distinguished platform brings together industry leaders and innovators to advance Construction Materials, Systems, Equipment & Technology under the theme COMET - Trailblazing the Future.
K-RIDE remains committed to driving sustainable, future-ready rail infrastructure for Bengaluru and beyond. #kride




![kride - Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction - ShareChat kride - Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction Citizens urge authorities expedite BSRP to The Hindu Bureau taken up war-foot- c on a particularly on Corri-| ing BENGALURU connecting the city dor 1 centre and the Kempegow- 0f citizens has] A group urged authorities to da International Airport: accel According to the group, erate work on the Bengalu- ru Suburban Rail Project the suburban rail project the long-awaited had been in discussion for BSRP), public transport initiative nearly four decades before getting the approval. Members of Citizens for Ho- Citizens met the Managing] wever; on-ground progress] Director of Rail Inifrastruic- remainS SlOW They Development Compa- noted that the coll- ture (Karnataka) Limited , struction of the Corridor 1, ny Lakshman Singh, the 40-kmn stretch, had not On Thursday and submitted a begun even ६५ months af- letter calling for work to be ter sanction - ShareChat](https://cdn4.sharechat.com/bd5223f_s1w/compressed_gm_40_img_490071_3456f980_1773396488851_sc.jpg?tenant=sc&referrer=user-profile-service%2FrequestType50&f=851_sc.jpg)


![kride - ರೈಡ್ U७U K RIDE = Q & A What does a "corridor" mean in a railway project ? A dedicated waiting hall connecting] B A rail route A key locations pedestrian subway ರೈಡ್ U७U K RIDE = Q & A What does a "corridor" mean in a railway project ? A dedicated waiting hall connecting] B A rail route A key locations pedestrian subway - ShareChat kride - ರೈಡ್ U७U K RIDE = Q & A What does a "corridor" mean in a railway project ? A dedicated waiting hall connecting] B A rail route A key locations pedestrian subway ರೈಡ್ U७U K RIDE = Q & A What does a "corridor" mean in a railway project ? A dedicated waiting hall connecting] B A rail route A key locations pedestrian subway - ShareChat](https://cdn4.sharechat.com/bd5223f_s1w/compressed_gm_40_img_35811_122ff506_1772604034487_sc.jpg?tenant=sc&referrer=user-profile-service%2FrequestType50&f=487_sc.jpg)