Amaravati Capital Updates
608 views
7 days ago
🔥 Krishna River Retaining wall Update 🔥 👉 300 + pilings completed out of 2000 •Wall hight 9 meters 40 /45 Depth Of piling •Per day Completing 10 To 15 piles •Target To Complete 2 years From Work Started •Wall bottom Wirth 1.8 meters Top Wirth 0.6 meters .Total wall 1.7 kms • Varadhi To Railway Bridge #Apcrda #Amaravati #AndhraPradesh #ShaikNayeemPasha #AmaravatiCapitalUpdates @prajarajadhani #📽ట్రెండింగ్ వీడియోస్📱